Building Fees

 

Building Permit Authority Fees

Fee $ (GST Exempt)

Building permit (includes certificate of completion)

 

Minor structures (non habitable) under $5000 building work value – examples (signs, poles, towers, solar panels and the like where not exempt under the Building Regulations)

50

  • <$25,000

125

  • $25,001 < $300,000

180

  • $300,001 < $500,000

250

  • > $500,001

500

Temporary occupancy permit

115

Building certificate

250

Tasmanian Building & Construction Industry Training Board Levy

0.2% (of value of building work)

Building permit levy

0.1% (of value of building work)

Permit to proceed or permit of substantial compliance

250% of building permit fee

Reduced rate of 150% of building permit fee if voluntarily reported and submitted

Environmental Health

 

Environmental Health Officer Report

335

Additional Inspections (EHO Report)

120

Planning Services Fees

 

Application for Planning Permit

Fee $ (GST Exempt)

Application for Planning Permit (Permitted s58 Land Use Planning and Approvals Act 1993)

 

Planning Permit Use or Development (minimum fee)

210

Minimum fee or development cost whichever is greater (per $1,000 of development cost) calculation capped at $5M

1 / 1,050

Council may review the development cost for the purpose of calculating fees with reference to construction guide costs.

 

Signage Permit (under Code E 7)

55

Permit required by requirement of a code only (other than E 7)

105

Application for Planning Permit (Discretionary s57 Land Use Planning and Approvals Act 1993)

 

Planning Permit (Use or Development) minimum fee

315

Minimum fee or development cost whichever is greater (per $1,000 of development cost) calculation capped at $5M

1.50 / 1,050

Council may review the development cost for the purpose of calculating fees with reference to construction guide costs.

 

Permit required by requirement of a code only (other than E 7)

155

Signage Permit (under Code E 7)

50

Public Notification fee

(added to all discretionary permit applications)

260

Level 2 Environmental Activity additional charge

420

Heritage Listed Additional Notification charge

55

Subdivision

315

+ 100 per additional lot

+ Public Notification

Adjustment of a boundary (Clause 9.2)

210

Examination and Sealing of Final Plan

180

Subdivision – 1 final inspection

120

Other

 

Examination and sealing of plans and documents

180

Amendment to permits or documents

180

Zoning certificate

55

Permitted or Exemption Certificate

55

 

 

Officer inspection/assessment (per hour – min 1 hour charge)

125

Preparation and issuing of LUPAA Section 64 (per hour)

125

Planning compliance certificate

300

 

 

Adhesion (or Discharge)

300

Strata Plan Certificate of Approval (s.36)

300

+30 per lot

Rezoning or Scheme Amendment

1,050

Applicant to pay all Planning Commission Costs and provide a report prepared by qualified planning consultant, and all costs associated with map production

 

Application for Dispensation under Part 3, Division 1A of Land Use Planning and Approvals Act 1993

In addition the application shall include all fees required by the Tasmanian Planning Commission.

1,000

Permit Applications Combined with an Application for Rezoning, Scheme Amendment or Dispensation.

Where an application is included for a combined dispensation, rezoning or scheme amendment and permit application, the application fee shall be determined with reference to the equivalent Planning Permit application fee.  The fee will be the greater of the fees, plus the fees required by the Tasmanian Planning Commission.

Minimum 1000

Note the Cost of Public Notification is included within the fees for rezoning, scheme amendments, or dispensation.

 

Plumbing Fees

 

 

Fee $ (GST Exempt)

Plumbing Permit

145

Plumbing Permit (stormwater only)

90

Plumbing Permit (water services only)

90

Special Plumbing Permit

 

Onsite Wastewater Management System

275

Trade Waste System (connected to sewer)

145

Trade Waste System (other than to sewer)

360

Connection of unregisterable relocatable building (section 77(g))

145

Grey water diversion/ recycling system (section 77(k)&(l))

145

Wet well / pump well (section 77(n))

145

Backflow Prevention Device

145

Amendment to permits

105

Other

 

Site and Soil Assessment Report

1,050 (inc. GST)

Site and Soil Evaluation

275 (inc. GST)

Inspection Fee

120